CURRENT TRANSMISSION PROJECTS UNDER CONSTRUCTION
Albany-Eugene Transmission Line Rebuild Project
[Linn and Lane counties, Ore. ]
BPA issued a final EIS in March 2012. The BPA administrator issued a ROD in June 2012 to proceed with the project. Construction began soon afterward. For more information, go to http://efw.bpa.gov/environmental services/Document Library/Albany-Eugene Rebuild
Creston-Bell Rebuild Project
[Lincoln and Spokane counties, Wash.]
BPA accepted comments on the preliminary EA through April 25, 2012, and published a FONSI in May. For more information, go to http://efw.bpa.gov/environmental services/Document Library/Creston Bell |
Pollution Prevention and Abatement (PP&A) organization provides environmental compliance and pollution prevention oversight for the operation and maintenance of BPA's transmission system.
PP&A oversees BPA transmission construction projects, implementing environmental measures and requirements identified during the environmental planning and analysis |
|
Big Eddy-Knight Transmission Project
[ Wasco County , Ore. , and Klickitat County , Wash. ] For information, go to www.efw.bpa.gov/environmental services/Document Library/Big Eddy-Knight |